Welcome to AU’s website for news and information about American University’s ongoing projects that are designed to help achieve our goal of “Building A Better American.” The various facilities projects presented on these pages, most of which were approved in our 2011 Campus Plan, support AU’s academic aspirations and enhance campus ambiance.

We invite students, faculty, staff, and neighbors to visit this site often for an overview of our building program, details about specific projects, and up-to-date information about all the ongoing construction and notice of any possible, temporary impact they may have on the community.

During the construction process, there may be temporary inconveniences that occasionally affect our neighbors and the university community. We will always strive to minimize the impact of our construction activity.

Construction Updates

AU Names Cassell Hall To Honor $3 Million Gift

Read more


Cassell Hall - Most Recent Update:

May 24, 2013 - Drywall installation on the northwest wing of the building is complete, and interior painting has begun. 

Interior electrical, mechanical, HVAC, and duct work continues. 

Interior drywall installation is almost complete on the upper floors. 

Fiber installation is under way. Sheetrock installation in wire closets is complete, and IT infrastructure installation is under way. 

Fan coil units have been installed. 

Stone veneer installation nears completion.   

Chilled water line installation is almost complete. Final chilled water interconnection to the building's cooling system is expected to be completed in the next two weeks. Construction of storm water cistern is complete. 

Gas service work is complete. 

Topsoil installation behind the President's Office continues. The planting plan approved in the zoning order is being finalized by OUA's Landscape Architecture Group. 

Telecommunications cable installation is under way.   

Nebraska Hall - Most Recent Update:

May 24, 2013 - Interior wall, duct work, electrical work and sprinkler systems installation continues. 

Terrace floor piping work continues.

Work on the sanitary line continues.

Brick masonry exterior work continues.

Window installation is approximately 50 percent complete.

McKinley - Most Recent Update:

May 24, 2013 - Roof deck concrete pour is expected to begin at the end of this week. 

Construction of the new steam line to service the building is expected to being on June 17 and be completed by the end of September. 

Construction of a new transformer vault is under way and is expected to be completed in the next two weeks. Utility work, including new electrical service, steam and chilled water interconnections, and storm water management system are under way.   

Interior shoring work is proceeding in preparation for the demolition phase of interior walls. 

Research for the removal and reuse of leftover marble pieces continues. 

Necessary permits are being obtained to remove two oak and sycamore trees located around and between McKinley and Bender Library. The trees will be removed as soon as the permits are granted. 

The walkway between McKinley Building and Bender Library will be closed after graduation for the entire summer to accommodate underground utility improvements, landscaping/hard-scaping, and other construction activities. 

Interior mechanical and electrical systems work is scheduled to begin May 24. 

Final furniture layouts are being developed.  

Tenley Campus - Most Recent Update:

April 5, 2013 - Coordination with Washington College of Law (WCL), for Office of Information Technologies and Public Safety requirements for the new campus continues.

Discussion on tree removal continues in coordination with OUA and Grounds department.

Review for construction is scheduled for April 17 and 18.

4401 Connecticut - Most Recent Update:

May 9, 2013 - Construction continues on the third, fourth, and sixth floors to accommodate WAMU and the University Communications and Marketing (UCM) department.  WAMU and UCM are expected to move into the building between the end of May and the middle of June. 